Glen Sannox ferry to enter Arran service as CalMac deals with ‘snags’

Originally due for delivery in 2018, the ferry and sister ship Glen Rosa have endured a saga of costly delays and technical problems at shipyard Ferguson Marine.

Glen Sannox will serve Arran and operate from Troon, South Ayrshire, with the Caledonian Isles ferry forming the other part of a two-vessel service to the island from Ardrossan, North Ayrshire, from March 28.

The 3000-tonne Glen Rosa is due to be handed over in September and costs for the two vessels are expected to be more than triple the original price tag of £97 million.

READ MORE: John Swinney apologises to islanders hit by over-budget ferries

However a report on Saturday suggests this handover will face a further delay to spring 2026.

CalMac said it is still dealing with a small number of issues on Glen Sannox, including oil contamination in a hydraulic system, which has forced the closure of a mezzanine deck.

The ferry operator says the closure will not affect capacity because of low demand over the winter period.

(Image: Jane Barlow/PA Wire)

Duncan Mackison, chief executive of CalMac, said: “Great effort has gone into getting MV Glen Sannox ready for service for Monday.

“It is testament to the commitment of people at CalMac to Arran that we’ve been able to reduce our original schedule for familiarisation and meet an ambitious target for entry to service.

“Launching a new major vessel is akin to buying a new-build house.

“You can move into a new home whilst some small snags are fixed, and we can operate MV Glen Sannox whilst we address a small number of minor issues that have no bearing on the safe operation of the vessel, or the experience passengers have on board.

“We are excited to welcome people on board and look forward to seeing a vessel which will bring great benefit to Arran enter service for the local community.”

READ MORE: Scottish Labour briefing notes on two child-cap and Waspi revealed

Discussing the reported delays to Glen Rosa, Ferguson Marine’s interim chief executive John Petticrew said: “No-one wants to see the swift and safe delivery of Glen Rosa more than Ferguson Marine and work is progressing on the vessel at pace as we speak.

“Now that Glen Sannox has been handed over, it’s crucial that we take time to review our plan for the delivery of Glen Rosa.

“As such, we are currently undertaking a lessons-learned exercise alongside our Scottish Government sponsor team, Lloyds, MCA, CMAL and CalMac.

“Only once this exercise is complete will we be able to provide a final estimated completion date for Glen Rosa.”

Image Credits and Reference: https://www.thenational.scot/news/24849947.glen-sannox-ferry-enter-arran-service-calmac-deals-snags/?ref=rss